Given the federal structure in the power sector, most states float tenders different from the Centre and adopt separate selection criteria, mostly tilting towards low cost.
Barring a few, all privately-owned thermal power units, roughly about 40,000 Mw, constructed over the past decade were built using Chinese equipment.
The first 2 GW of generation capacity will start by 2022, with the rest installed in 2-GW annual increments through 2025, Adani said
ReNew quoted a winning tariff of Rs 2.9 per unit (kwh) for the complete capacity of 400 Mw offered by the government.
Supply chain disruption due to Corona to be considered Force Majeure
Over 3 GW of solar power projects, awarded in 2018-19, will face delay in commissioning
AP Green Energy Corporation will be incorporated as a wholly owned subsidiary of the state-owned power utility AP Genco for the purpose of developing the 10,000 mw solar power project
Solar modules constitute 80% of the cost of a solar power project.
The deal, expected to be closed by the first half of 2020, is estimated to help ENGIE reduce its debt by Euro 400 million
With project developers cutting down on projects, heat is felt by panel manufacturers as well
Government-to-government negotiations were held on Wednesday and it was decided that 25 concrete projects would be carried out between the two countries
Rooftop solar installations declined by just 16 per cent quarter-over-quarter (QoQ) in Q3 2019, totaling 245 MW compared to 292 MW installed in Q2 2019
State govt cancelled clean energy projects in July, citing wrong bidding
These solar panels are fixed atop vehicle roofs to act as supplementary power source for electrical load demand without impacting the vehicle's aerodynamics
UPERC sets new benchmark in lowest solar power tariffs in the state
Adityanath government targetting renewable energy capacity of 10,700 mw
India is aiming to install 100 Gw of solar power by 2022, of which 40 Gw is to come from solar rooftop
With a planned production of nearly 1,200 GWh per year, these solar PV projects will generate the energy required to meet the annual electricity needs of 1.1 million Indian households
The polluting fuel will continue to produce half of the country's electricity by 2030, compared with about 72% now
Wafers, cells, modules manufacturing & imported panels for power plant allowed